Project Progress

Phase 1 of the proposed drainage improvements were completed in 2018. 

Phase 2 was initially designed and nearly fully permitted in 2019. This original design consisted of complex drainage structures designed to avoid conflict with some of AT&T’s major duct banks under Playground Road. However, due to ongoing and extensive coordination with AT&T, and AT&T’s decision to relocate their utilities along Playground Road, the proposed drainage improvements were redesigned accordingly. The redesign of Phase 2 is complete and is in the permitting process. 

Phase 2 began construction in September 2022 and will be divided into two parts, 2A and 2B. 

Phase 2A begins at the West Ashley Bikeway and extends north parallel to Playground Road, then west across Playground Road at Fifth Avenue.

 Phase 2A is expected to start on or about September 1st, 2022. Within the first 3 months, the contractor will be preparing for infrastructure installation by staging materials, installing soil erosion measures, clearing trees and debris, demolishing structures, and performing investigative work.

Once this construction preparation is complete, the contractor will begin the improvements at Playground Road and Fifth Avenue. Additional information to follow regarding road closures and detours in this area. Phase 2A is expected to be complete by the end of 2023.

Once Phase 2A is complete, Phase 2B will begin. Phase 2B starts after the crossing of Playground Road on the northwest side and extends along the St. Andrews Parks and Playground property then extends nearly to Ashley River Road. The project also improves the existing channel between the Palmilla Apartments and the N. Forest Acres neighborhood. Phase 2B is expected to start by summer 2024. 

The proposed improvements consist of improvements to the existing open channel, installation of large diameter box culverts, and the installation of new, piped drainage systems along Playground Road and Brookwood Circle. 

Project Phases Map-1


  1. Anthony Giralo, PE

    Senior Engineering Project Manager

  2. Robin Kidd

    Stormwater Outreach Coordinator

  3. Stormwater Management

    Physical Address
    2 George St
    Suite 2100
    Charleston, SC 29401

    Mailing Address

    Charleston, SC 29402